Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the easy-fancybox domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/langstoneconstruction.co.uk/httpdocs/wp-includes/functions.php on line 6114

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the fakerpress domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/vhosts/langstoneconstruction.co.uk/httpdocs/wp-includes/functions.php on line 6114
Y Pant Comprehensive School - Langstone Construction Group

Langstone Construction are hiring – more

Client: RCT Council Duration: June 2015 - December 2017 Cost: £19m Procurement: JCT Design & Build procured through the SEWSCAP framework Designers: Boyes Rees Architects. Opus Engineers

Y Pant Comprehensive School

Project Description

Client: RCT Council Duration: June 2015 - December 2017 Cost: £19m Procurement: JCT Design & Build procured through the SEWSCAP framework Designers: Boyes Rees Architects. Opus Engineers

Secured under the SEWSCAP Framework, in partnership with Rhondda Cynon Taf County Borough Council. The state-of-the-art 8,743m2 facility replaced the old and outdated previous campus with the design and construction of a 1,400-capacity comprehensive school, including a 300-pupil sixth form.

Working next to the existing school, which remained live throughout the scheme, the project comprised the construction of a new two-storey teaching facility, a 3G sports pitch to FIFA stage 1 recommendations, a new Multi Use Games Area, two grass football pitches, and a grass rugby pitch. The project also included the refurbishment of the existing drama and sports facilities – the only part of the existing campus that remained.

Following the completion of the new build and a safe transition of pupils into their new facility, the team commenced demolition of the old facilities, to leave the school with a transformational learning campus fit for the 21st Century.

Challenges

  • Shared site access
  • Live environment
  • Sympathetic to student exam schedule
  • Challenging programme
  • Sub-contractor insolvency
  • Refurbishment phase in an occupied building and to a challenging timeframe
  • Constrained decant and occupation programme
  • Challenging weather conditions
  • Uncertainty on the extent of asbestos

Social Value & Community Engagement

During the construction period, we participated in several community engagement and social value events.

  • Dedicated pupil ‘reporters’ visited the site creating updates for the school to keep everyone up to date on progress.
  • Special “Dear Neighbour” newsletters also kept everyone in the school and the surrounding community up-to-date.
  • The project team also formed a partnership with the Pontyclun Food Bank to make regular donations.
  • The team held ‘Meet the Buyer’ events held during the project.
  • Charity football match with the school v the construction team raising over £2000.
  • Continued providing work experience and apprenticeship placements